Construction Update as of 1/24/19
Construction Update as of 12/20/18
Construction Update as of 12/13/18
Construction Update as of 11/1/18
Construction Update as of 10/25/18
Construction Update as of 10/11/18
Construction Update as of 9/27/18
Construction Update as of 9/13/18
- Install of DVR system completed
- Install of classroom phones, tech devices in progress
- Install of smartboards to begin the week of 1/28
- Install of interior camera and devices completed.
- Install of fire alarm and pa devices completed
- Install of corridor VET completed
- Install of markerboards and tackboards completed
- Install of door hardware in progress
- Install of interior camera and devices to be completed by 1/4/19
- Install of fire alarm and pa devices in progress
- Install of ceiling tile completed in corridor
- Install of markerboards and tackboards completed
- Install of corridor VET in progress
Construction Update as of 12/20/18
- Install of interior camera and devices to be completed after the holiday break
- Install of fire alarm and pa devices in progress
- Install of ceiling tile completed in classrooms
- Install of door hardware in progress
Construction Update as of 12/13/18
- Install of ceramic tile complete
- Rough in of data, FA an PA wire in progress
- Install of ceiling tile completed in MP addition
- Install of casework and countertops in progress
- Install of plumbing fixtures in progress
- Install of interior camera and devices in progress at Manorhaven
- Manorhaven project is on target to be completed by the first week of February
- Install of ceramic tile approximately 90% complete
- Rough in of data, FA an PA wire in progress
- Install of ceiling grid and tile cuts in progress
- Install of casework in progress
Construction Update as of 11/1/18
- Temperature control wiring completed
- Primer/block filler install completed
- Window install in progress
- Rough in of data, FA an PA wire in progress
Construction Update as of 10/25/18
- Temperature control wiring install in progress
- Asphalt final course, parking lot completed
- Primer/block filler install in progress
- Window install to begin on Friday, 10/26
Construction Update as of 10/11/18
- Rough-in of circuit wire in progress
- Temperature control wiring install in progress
- Asphalt binder course installed on 10/8. Final course to be installed on Saturday, 10/20/18
Construction Update as of 9/27/18
- Rough-in of circuit wire in progress
- Temperature control wiring install in progress
Construction Update as of 9/13/18
- Rough-in of circuit wire in progress
- Windows scheduled for delivery in mid-October
- Brick completed
- Water service installation completed